Sterlite Power has announced the successful commissioning of its green energy corridor project – Lakadia-Vadodara Transmission Project (LVTPL). The project aims to deliver more than 5,000 MW of power from renewable rich regions of Bhuj and Kutch to the national grid – a step towards accelerating India’s transition towards a greener economy.
Built with an investment of Rs 2,024 crore, this inter-state transmission connects the 765/400 kV substation at Lakadia to Vadodara through a 335 km long 765 kV double-circuit transmission line. With 812 towers spanning seven districts in Gujarat, this power transmission corridor is also one of the largest transmission corridors built in India till date. Additionally, it forms a critical part of the world’s largest 30,000 MW Hybrid renewable energy park coming up in Kutch.
Pratik Agarwal, Managing Director, Sterlite Power, expresses pride in announcing the completion of the mega LVTPL project. He shares that it has been a challenging journey, but the company has been successful in unlocking 5,000 MW of green power for the nation that will accelerate India’s RE vision of 500 GW by 2030.”
Manish Agarwal, Director & CEO-India Transmission, Sterlite Power, expresses his gratitude to the Government and the local administration for their constant support in ensuring the successful completion of the critical project.
The project was awarded to the company in 2019 and the work started in 2020, during COVID-19. True to its innovative spirit, the company implemented innovative construction techniques like pocket foundation, well point system, and unique tower designs to construct durable power infrastructure that could withstand the complex terrain challenges in the region.
During the project execution phase, Sterlite Power engaged with various communities for an inclusive approach towards development. It also provided employment to thousands of skilled and unskilled people during the construction phase. It also made concerted efforts to provide essential health items to vulnerable communities around the project sites during the COVID-19 imposed national lockdown.